Sewer Rehabilitation Project

The Sewer Rehabilitation Project was completed in 2015 and consisted of two phases: sewer rehabilitation and manhole rehabilitation. The project fixed cracks and leaks in the sewer system to prevent infiltration of ground water and surface water into the sewer system.

West Main Street Sewer Rehabilitation

Sewer rehabilitation took place along West Main St. from Radford St. to Hickory Drive. Approximately nine manholes and eight sewer lines were repaired.

Manhole Rehabilitation

Manhole rehabilitation repaired 37 sewer manholes at various locations throughout town.

This project was completed in Spring 2015.