Roanoke Street Sidewalk Extension - 460 Bypass

This project will construct a five-foot wide sidewalk, curb and gutter, safety lighting, crosswalks, crosswalk signals and flashing beacons between Falling Branch Road and Hubbel Drive. 

Roanoke St_Final_10-31-17

Overview

  • Purpose – Provide a pedestrian route along Roanoke Street to navigate under US 460 By-Pass
  • Total Length of Project – 1,050 feet
  • From – 600 feet East of Falling Branch Road
  • To – Hubbell Drive

Estimated Project Cost 

Total Estimated Cost: $801,885

  • Preliminary Engineering (PE): $174,289
  • Right of Way & Utilities (RW): $9,100
  • Construction (CN): $618,496

Total Funding Allocation: $801,885

  • Highway Safety Improvement Program (100% Grant): $490,169
  • Transportation Alternatives (80% Grant): $249,373
  • Local TA Funds Match (20% Match): $62,343

Anticipated Schedule

  • Right of Way Acquisition & Utility Relocations: September 2020
  • Begin Construction: November 2021

A link to the 50% plan submittal is available here.  The improvements shown thereon do not indicate that improvements to a property are imminent or that a decision on an improvement has been made.

A link to the National Environmental Policy Act (NEPA) document in the form of a Programmatic Categorical Exclusion is available here.

Willingness to Hold a Public Hearing: No Responses

A willingness to hold a public hearing advertisement was placed requesting resident interest in the Town holding a public hearing for this project until May 4, 2020. No responses were received from the ad. Therefore, no public hearing will take place.