Beginning the evening of May 22, crews will begin paving the segment of Roanoke Street from Depot Street to the US 460 Bypass Interchange. The work is expected to take approximately two weeks, and crews will be paving during night hours to limit traffic impacts.
Roanoke Street Paving Timeline
Note: These are estimates to when these paving projects will begin.
Spring 2019 COMPLETE
Paving of Roanoke Street from John Lemley Lane to the I-81 Exit 118 C Interchange
Spring 2022 IN PROGRESS
Paving of Roanoke Street from the I-81 Exit 118 B Interchange to Depot Street
Fall 2022/Spring 2023 UPCOMING
Paving of Roanoke Street from the I-81 Exit 118 C Interchange to the I-81 Exit 118 B Interchange
Spring 2023 UPCOMING
Replacing waterline under Roanoke Street from Depot Street to Main Street
Fall 2023/Spring 2024 FUNDING PENDING
Paving of Roanoke Street from Depot Street to Main Street