The Christiansburg Aquatic Center is upgrading its HVAC system. The preparatory work has begun and contractors will be completing physical construction of the project in two phases. The timeline of work is subject to change dependent on weather and supply chain availability. An overview of the project and a tentative timeline are below.

Phase One

September 2025 - March 2026

Phase 1A - Intermittent facility closures

During this phase an additional mechanical yard will be constructed in the rear of the facility. This phase will also include the installation of the standalone unit, enlarged duct work and preparations for Phase 2. 

  • Grading
  • Installation of standalone unit
  • New enlarged duct work

October 2025 - April 2026

Phase 1B - Partial facility closure

Both the Leisure and Therapy pools will be closed beginning Oct. 27, 2025.  During this time, the fitness room and multi-purpose room will remain open during public hours. For information on available classes, please visit www.cacpool.com. The competition pool will also be in operation during this phase. Crews will be working on excavating and enlarging the mechanical yard in front of the facility and enlarging the duct work over both pools. 

  • New unit added 
  • Enlarged and upgraded mechanical yard
  • New enlarged duct work

Phase Two

Summer 2026

Phase 2 - Temporary partial closure

The Competition Pool is scheduled to be closed the during the month of May. The fitness room and multi-purpose room will remain open during public hours. For information on available classes, please visit www.cacpool.com.

  • Replacement of remaining HVAC units
  • Additional grading
  • New enlarged duct work
Phase/WorkImpacted AreaEstimated Closure Time
Phase 1AOutside of Aquatic CenterNone
Phase 1BLeisure & Therapy poolsOct. 2025 - Apr. 2026
Phase 2Competition PoolMay 2026


As this project progresses, the Town will continue to provide updates and timeframes. Please check this page regularly for the latest information. 

  1. 1 Updated progress on the Aquatic Center HVAC project
  2. 2 Updated progress on the Aquatic Center HVAC project
  3. 3 Updated progress on the Aquatic Center HVAC project
  4. 4 Updated progress on the Aquatic Center HVAC project
  5. 5 Screenshot 2025-09-18 104824
  6. 6 Screenshot 2025-09-18 104802
  7. 7 Screenshot 2025-09-18 104957
  8. 8 IMG_0052
  9. 9 IMG_0051
  10. 10 Resized_20251029_105309
  11. 11 IMG_8582
  12. 12 IMG_7115
  13. 13 IMG_0111
  14. 14 IMG_0118
  15. 15 IMG_9377
  16. 16 IMG_0181
  17. 17 IMG_0186
  18. 18 IMG_0178
  19. 19 IMG_0127
  20. 20 IMG_0137
  21. 21 IMG_0132
  22. 22 IMG_0173
  23. 23 IMG_0188